29 Beaucroft Lane, Wimborne

In Wimborne, a notable replacement and extension of a garage was completed ahead of its anticipated schedule. Initially projected to span a week, the project was finished within two days. The outcome is a spacious double garage, now boasting an area of 56 square meters, enhancing the property’s functionality and aesthetic.
The completion of this project was made possible through our 8-ton Kubota x60 (Excavator), allowing for the installation of 17 screwpiles, each delving to an average depth of 5 meters, laying a foundation for the extended structure.
This project was in collaboration with MPS Building LTD, setting the standards for residential projects in the south coast.

ScrewPiling UK provided 17 Screwpiles at 5 metres & 76mm using our 8 ton excavator  

MORE PROJECTS

22 Crichel Mount, Sandbanks

In our recent residential extension project, 22 screwpiles were installed to strategically enhance the existing garage and terrace area. Executed by the dedicated team at Screwpiling UK for MPS Building Contractors, the renovation achieved an average depth of 6 meters for each 76mm diameter screwpile within a remarkable 1-week timeframe, surpassing expectations. The project utilized our 8-ton Kubota excavator, demonstrating efficiency and excellence in execution.

Rosebank Way, Acton

Nestled in North Acton, West London, within the London Borough of Ealing, Rosebank Way is at the heart of a dynamic revitalization, fuelled by the upcoming Elizabeth Line (Crossrail) from Acton Main Line. Serving as a catalyst for ongoing investment, the transit project is set to boost connectivity and has the potential to elevate property values and spur economic activity.